Intersection Traffic Signal Work (in the area and beyond) - Traffic Disruptions due to the Work - the Week of July 23, 2023 Read more inside this post.
Traffic Signal Work will take place at the following intersections the week of 7/23/23. Work will be at night from 7:00pm-5:00am, with no lane closures to occur before 9:00pm. The intersections will be upgraded as part of NHDOT State wide signal contract X-A004(978) 42878.
Signal ID Town Intersection
S-007-02 Allenstown US 3/ School St
S-007-03 Allenstown US 3/NH 28
S-037-04 Bedford US 3/Hawthorne Dr/ East Pont Exec Center
S-037-08 Bedford US 3/ Commerce Dr/ Technology Dr
S-037-09 Bedford New Boston Rd/ Wallace Rd
S-037-12 Bedford NH 101/Jenkins Rd/ Hardy RD
S-039-01 Belmont NH 106/ NH 104
S-039-04 Belmont NH 106/Plummer Hill Rd
S-169-01 Gilford NH 11/NH 11B
S-169-02 Gilford NH 11/NH 11C (Lily Pond)
S-255-01 Lee NH 125/ Market Basket Ent/ Express Car Care
Work will consist of adding Flashing yellow arrows to these intersections, changing out controllers, MMUs and other cabinet components. Each of these locations should take about 1 night to complete.