Aerial Slideshows of Hillsbrook Village

Route 28 & Chester Turnpike

Construction Progress on the Assisted Living Facility

Dateline: Nov. 21, 2021

The following slideshow shows the latest aerial view of the construction site photographed by the Hillsbrook Village drone. Although the photos show that roof sheathing was installed on 3/4 of the building, within a few days, the entire building was covered with sheathing or shingles. The final photo gives a scenic view of Route 28 leading to the mountains to the north.

slideshow  SLIDESHOW 11/5 to 11/18/21 


Optimus Senior Living provided the following construction updates.

  • Roof sheathing was completed almost to the north end; roof shingles installed over the south half.
  • Temporary power from the street has been installed in temporary breaker boxes. That's why you can see lights in the building at night. Permanent three-phase power is planned for next May.
  • Shower units are to be delivered in four shipments over the next few weeks.
  • The first third of the facility is undergoing final building inspections.
  • After those inspections are completed, that third of the building is to be insulated.
  • Drywall installation in the first third of the building is planned to start in December.
  • Roadway construction and landscaping are ongoing.

Dateline: Sept. 29, 2021

The following slideshow gives you a bird's eye view of the construction site. Aerial photos taken by a drone give a more impressive perspective on the work under way at Hillsbrook Village.

  SLIDESHOW 9/29/21slideshow
 

The following details about the construction site were obtained from Optimus Senior Living.

  • Eighteen framers are working to get the complete building shell and roof completed by December.
  • To increase productivity, 8x8 foot wall sections are being built offsite and installed onsite.
  • The retaining walls along the roadways and parking areas have been built.
  • Underground drainage has been installed.
  • Grading is being done to establish retaining ponds for stormwater runoff.
  • For the parking lots, the goal is to have the base coat of pavement done by mid-November.
  • Natural gas piping is being brought in so they can heat the building for the workers over the winter.

What You Can Do

Keep checking this site for periodic updates. Stop by the sales office. It is located in Unit 4 behind the Elliot Family Health Center at 50 Pinewood Rd. (Route 28).